Project: St Marys Road - Installation completed
Project description: Volther PowerTherm PVT installation.
The use of PVT for this project was in order to conform with the Merton rule which insists any new building being built in the borough produces a % of its energy from onsite generation.
Merton Council's acceptance of the technology for this application sets a precedent in the UK.
PowerTherm PVT panels:
System size 21.35m2 2.3kW (pk)
| Annual output electrical | 2,988kWh |
| Annual output thermal | 8,897kWh |
Net Outputs
| Electrical | 2,242kWh/annum |
| Thermal | 7,100kWh/annum |